Tugas Penjadwalan
1. Priority Scheduling
Proses | Burst Time (ms) | Prioritas |
P1 | 7 | 3 |
P2 | 2 | 4 |
P3 | 3 | 3 |
P4 | 2 | 1 |
P5 | 10 | 2 |
P4 | P5 | P1 | P3 | P2 |
0 . . . . .2 . . . . . . . . . . . . . . 12 . . . . . . . . 19 . . . . . . 22 . . . . .24
Proses | Waiting Time (ms) |
P1 | 12 |
P2 | 22 |
P3 | 19 |
P4 | 0 |
P5 | 2 |
AWT = (12+22+19+0+2) / 5 = 11 ms
2. FCFS & Round Robin, dengan Q = 3
Proses | Burst Time (ms) |
P1 | 23 |
P2 | 6 |
P3 | 6 |
P1 | P2 | P3 | P1 | P2 | P3 | P1 | P1 | P1 | P1 | P1 | P1 |
0 . . 3 . . 6. . . 9. . . 12. . . 15. .18. . 21 . . 24. . 27. . 30. .33. .35
Proses | Waiting Time (ms) |
P1 | 0+(9-3)+(18-12) = 12 |
P2 | 3+(12-6) = 9 |
P3 | 6+(15-9) = 12 |
AWT = (12+9+12) / 3 = 11 ms
3. SRF (Shortest Remaining First)
Proses | Arrival Time | Burst Time (ms) |
P1 | 0 | 8 |
P2 | 3 | 4 |
P3 | 4 | 9 |
P4 | 7 | 5 |
P1 | P2 | P1 | P4 | P3 |
0 . . . . .3 . . . . . . . 7 . . . . . . . . 12 . . . . . . . 17 . . . . . . . . 26
Proses | Waiting Time (ms) |
P1 | 0+(7-3) = 4 |
P2 | 3-3 = 0 |
P3 | 17-4 = 13 |
P4 | 12-7 = 5 |
AWT = (4+0+13+5) / 4 = 5.5 ms